IBS Conferences

IBS HQ Construction Overview

IBS HQ Construction Overview
Item Details
Project title The First Construction Project of IBS HQ
Site location 3-1 Doryong-dong Yuseong-gu Daejeon (Block 1-5 of the District-unit Planning Zone)
Area/District Semi-industrial Area, the District-unit Planning Zone to utilize Daejeon EXPO area
Purpose of use Facilities for education and research (research institutes, libraries and dormitories)
Plot size 200,641㎡
Main structure Reinforced Concrete Construction
Number of floors Seven stories and one underground level
Building area 22,710㎡
Total floor area 72,409㎡ / above ground: 61,288㎡, underground level: 11,122㎡
Total area for calculation of the floor area ratio 61,288㎡
Building-to-land ratio 11.32%Legal criteria50%
Floor area ratio 30.55%Legal criteria300%
The number of cars to be parkedPlanned 602 (166.30% of legal requirement, including 26 for the disabled)
Legal requirement 362 (11 for the disabled) - Facility for education & research: 1 car/200㎡
Calculation criteria 72,409㎡/ 200㎡= 362.04
Landscaping areaPlanned 100,096㎡(49.88%)Legal criteria30,096㎡
Calculation criteria More than 15% of plot size
Natural groundPlanned 99,862㎡
Calculation criteria More than 10% of landscaping area
Major exterior materials THK24 double glazed units containing low-emissivity glass, THK24 insulating glass, extruded cement panel, sprit blocks, granite, aluminum composite panel
Building equipmentMachine equipment Central heating and cooling (geothermal heat, steam boiler)
Electric equipment Single line from KEPCO, photovoltaic power generation, mutual backup system for transformers, LED lighting (more than 60%), socket-outlet to cut-off standby power(more than 30%)
Communication equipment Equipment for structured wiring, switching apparatus, TV, CCTV, and broadcasting
Fire-Fighting equipment Equipment for automatic fire detection, sprinkler, standpipe and hose station, fire extinguisher

(Unit : ㎡)

Main Building, Animal laboratory, Guest House ...
Items Main Building Animal laboratory (Bldg. D) Guest house (Bldg. E) Library (Bldg. F) Security bldg. (Bldg. G) Total
Admin. bldg. (Bldg. A) Experimental research bldg.(Bldg. B) Theoretical research bldg. (Bldg. C)
Subtotal
by
Building
7F 786 786
6F 786 786
5F 1,317 786 2,103
4F 1,288 3,301 1,585 786 6,962
3F 1,618 3,980 6,480 165 788 1,908 14,939
2F 1,813 4,055 6,483 111 602 2,088 15,152
1F 1,067 5,790 7,634 3,212 749 2,066 41 20,559
Subtotal by Building 7,103 17,126 22,182 3,488 5,285 6,062 41 61,287
Subtotal 61,287
Basement floor B1 2,404 3,947 2,449 1,286 270 765 11,122
Subtotal by Building 2,404 3,947 2,449 1,286 270 765 11,122
Subtotal 11,122
Total floor area 9,507 21,073 24,631 4,774 5,555 6,828 41 72,409
Grand total 72,409